Installation of the jetty under the railway bridge, to connect the footpath between Stourbridge Common and Ditton Meadows, is now scheduled to take place from 13th to 26th August. During this period there will be some river closures and some disruption on Fen Road, Chesterton. Most of the work is planned to be carried out during the day, but there will be two occurrences of night working.
Further detail as supplied by the Greater Cambridge Partnership is shown below. The dates are subject to change.
Dates |
Times |
Restrictions |
13 - 14 August |
08:00 - 18:00 |
Full river closure |
14/15 August |
08:00 - 18:00 |
Fen Road: lane closure via stop/go boards and the towpath will be closed for a short duration |
15 - 16 August |
15th: 08:00 - 18:00
20:00 on 15th to 06:00 on 16th |
Full river closure |
17 - 18 August |
08:00 - 18:00 |
Full river closure |
17 August |
08:00 - 18:00 |
Pike and Eel on Fen Road: lane closure via stop/go boards and the towpath will be closed for a short duration
Vehicle movements on Fen Road
Lane closure on Fen Foad and the towpath will be closed for a short duration. |
19 August |
08:00 - 18:00 |
Full river closure |
20 - 21 August |
08:00 - 18:00 |
Full river closure |
22 - 23 August |
20:00 on 22nd to 06:00 on 23rd |
Full river closure
Towpath will be closed for a short duration. |
24, 25, 26 August |
08:00 - 18:00 |
Full river closure |
24/25 August |
08:00 - 18:00 |
Lane closure on Fen Foad and the towpath will be closed for a short duration. |
If you wish to discuss this work and how it affects you, please contact Tarmac’s Project Manager, Alex Bedford at alex.bedford@tarmac.com or via the out of hours number: 0800 876 6087.